Skip to main content

How we calculate initiative financials

Written by Sanders Lazier

1. How to read the page

An initiative's Overview shows two cards, and they answer two different questions.

Card

Question it answers

Period covered

Expected Total Project Impact

If everything goes to plan, what will this project deliver over its whole life?

The entire project, start to end of useful life

Project Performance to Date

How is it actually tracking against that plan so far?

Only the months that have finished since the project completed

The first card is a forecast. It never changes unless someone edits the project's inputs. The second card is a measurement. It grows each month as more real data arrives.

Important exception: two rows in the second card — Simple payback and Discounted payback — do not follow the "to date" rule. Both sides of those two rows cover the whole project life. Section 8 explains why, and the reason is a good one, but it is an exception to the card's heading.

2. The worked example

Every formula in this article is worked through with the same project example, so you can follow one set of numbers from beginning to end. These are the project's recorded inputs.

Input

Value

What it is

Start date

1 Jan 2024

The day work begins and money starts being spent

Completion date

31 Dec 2025

The day construction or installation finishes

Useful life

3 years

How long the equipment will keep producing savings

Planned capital cost

$1,000,000

What we expected to spend to build it

Actual capital cost

$800,000

What was actually spent

Planned annual savings

$550,000 / year

The energy cost we expected to avoid each year

Baseline emissions

52,046 tCO2e / year

What the site emitted before the project, measured

Expected reduction

50%

How much of those emissions the project should remove

Discount rate

12%

See section 5

Date being viewed

August 2026

"Today", for the purposes of this example

Jargon — baseline: the baseline is the "before" picture — what the site was emitting or spending before the project changed anything. Every saving is measured as the difference from this. If the baseline is wrong, every saving figure is wrong, which is why section 10 flags incomplete baselines as a risk.

Jargon — capital cost (capex): capital cost, often shortened to capex, is the one-off money spent up front to build or install something. It is separate from the ongoing running costs. In this model the entire capital cost is treated as being spent in the project's first month.

Jargon — useful life: the useful life is how many years the equipment is expected to keep working and producing savings. We do not count any savings after the useful life ends. If a project has not repaid its cost by then, we report that it does not pay back rather than assuming it will continue.

3. The project timeline

Almost every mistake in this kind of calculation comes from being unclear about when something starts. There are two separate things to understand about timing: when things happen, and how much a dollar is worth at each point on that same timeline.

When things happen. For the worked example:

  • January 2024 — the whole $1,000,000 is spent, in the project's first month.

  • January 2024 – December 2025 — the build period: 2 years, no savings yet.

  • Build ends 31 December 2025 → savings start 1 January 2026.

  • January 2026 – December 2028 — saving money: 3 years (the useful life).

  • January – July 2026 — measured so far: 7 finished months. "Today" is August 2026; August is not counted because it has not finished.

  • Payback is measured across the whole span, from January 2024 to December 2028.

The build period produces no savings by design, and that is why payback is measured from the day the money leaves the bank rather than from the day savings begin — the two years spent building are two years of waiting to be repaid.

What a dollar is worth at each point. Money arriving later is worth less to us than money arriving now, so before adding anything up we reduce future amounts. This is called discounting, and section 5 explains it fully.

The reduction does not begin immediately. There is a cushion of twelve months at the start, during which every dollar counts in full. Only after that does the reduction begin, and it grows the further into the future you go. In the worked example (a 12% discount rate, valued in January-2024 money): every dollar from January to December 2024 counts in full; the reduction starts in January 2025; $1 saved in January 2026 (the first savings month) counts as $0.88; $1 saved in December 2028 (the last savings month) counts as $0.64.

What this means for this particular project: the cushion covers January to December 2024, and this project does not start saving anything until January 2026 — well past it. So every dollar this project ever saves is reduced before it is counted — the cushion gives it no benefit at all. That is a direct consequence of spending two years building. A project that started saving within its first year would have some of its savings counted in full.

4. Exact date boundaries

These four rules decide which months are counted. Each one is stated as precisely as possible, because being off by a single month changes the answer.

Rule 1 — Savings begin the month after completion

The completion date is 31 December 2025. Savings are counted from 1 January 2026, not from December 2025.

Why: December 2025 is a month in which construction was still finishing. Counting it would credit the project with a month of savings it could not have produced.

First benefit month = the first day of the month following the completion date

Rule 2 — Only complete calendar months are measured

"Today" is August 2026. The measurement window ends on 31 July 2026. August is excluded.

Why: a month that is only part-way through has only part of its bills in. Including it would make every figure look worse than reality, and would make the whole table drift downward through the month and jump back up on the 1st. Excluding it keeps the table stable and honest.

Measurement window = first benefit month → last complete calendar month
For this example  =  January 2026 → July 2026  =  7 months

Rule 3 — The month in which a total crosses zero is counted

This rule applies to the payback figures. If the running total stands at −$8,000 at the end of one month and +$3,000 at the end of the next, the project broke even during that second month. That second month is included in the count.

Why: the alternative would report the project as not yet paid back in a month where it demonstrably was. We do not estimate a part-month; we count whole months only, matching the reference spreadsheet this model was built against.

Rule 3 with this project's real numbers:

Month

Saved that month

Running total

Result

Month 45

Sep 2027

$45,833.33

−$37,500

Still short. Not paid back

Month 46

Oct 2027

$45,833.33

+$8,333

Crossed zero during this month

Simple payback is therefore 46 months, or 3 years 10 months. The project did not become profitable at the end of month 46 — it crossed zero at some point during it — but we report whole months, so month 46 is the answer.

Rule 4 — Nothing is estimated beyond the useful life

The benefit period ends December 2028. If a project has not repaid its cost by then, we display "Does not pay back" rather than projecting further savings.

Why: the equipment's expected working life is the honest limit of what we can claim. Extending past it would be inventing savings.

What "Does not pay back" means precisely: it means the cost is not recovered within the equipment's useful life. It does not mean the project can never pay back. If the equipment lasts longer than expected, or savings improve, the picture changes. The phrase is scoped to the modelled life and nothing beyond it.

5. Discount rate and anchor

Jargon — discounting: discounting is the practice of treating money received in the future as worth less than money in hand today. If you have $100 now, you could invest it; $100 arriving in three years cannot have been invested during those three years, so it is worth less to you now. Discounting converts future amounts into today's equivalent so they can be fairly added together.

The rate we use

The discount rate is taken from the first of these that has been set:

  1. The rate set on this specific initiative — if not set → Platform default

  2. The company's default rate — if not set → Platform default

  3. 12% — the platform default

Where 12% comes from: It is a fallback, not a recommendation. Any company that has a formal cost of capital should set its own rate, and any initiative with a different risk profile should set one on the initiative itself.

The anchor

Jargon — valuation anchor: the anchor is the month whose money everything is expressed in. Saying "$243,010" is incomplete without saying which year's dollars. The anchor answers that.

On the initiative detail page, the anchor is the project's own start month — January 2024 in this example. This is shown on the card as "Valued at Jan 2024".

Why the start month: this page is about one project's own economics, and the question being asked is "was this a good investment decision?". That decision was made at the start, so the start month is the fair reference point. It also means the number does not move: opening this page today and again in six months shows the same figure, which makes it usable as a record.

The Scenario Planner uses a different anchor — on purpose. The Scenario Planner values everything in today's money instead. That is because it compares and adds up many initiatives at once, and initiatives that started in different years cannot be added together unless they are all converted to one common point in time. This means the same initiative can legitimately show a different value on the two pages. Both pages state their anchor on screen so the difference is visible rather than surprising.

How much a future dollar is reduced by

The reduction does not start straight away. The anchor month itself, plus the 11 months either side of it, are counted in full — every dollar in that period is worth a whole dollar. We call this the cushion. Beyond it, the reduction begins and grows with distance.

For this project the anchor is January 2024, so January to December 2024 is the cushion and the reduction begins in January 2025. The rule works in both directions: a month 11 months before the anchor would also be counted in full.

The adjustment factor:

Let  Months From Anchor  =  number of months between the anchor and the month being valued
                            (negative if before the anchor, positive if after)If  |Months From Anchor|  is 11 or fewer:
     Adjustment Factor = 1              (counted in full — no reduction)If the month is AFTER the anchor by more than 11 months:
     Adjustment Factor = 1 ÷ (1 + Discount Rate) ^ ((Months From Anchor − 11) ÷ 12)If the month is BEFORE the anchor by more than 11 months:
     Adjustment Factor = (1 + Discount Rate) ^ ((|Months From Anchor| − 11) ÷ 12)

Why there is a cushion at all: Amounts inside roughly a year of the anchor are treated as near enough to now to need no adjustment.

Why the −11 in the formula: the countdown starts at the edge of the cushion, not at the anchor. A month falling one month past the cushion is reduced by one month's worth, not a full year's. Without this, values would drop sharply the moment they crossed the boundary instead of easing down.

Worked example of the factor (anchor January 2024, discount rate 12%):

Month being valued

Months from anchor

Factor

Meaning

Jun 2024

5

1.0000

Inside the cushion — counted in full

Dec 2024

11

1.0000

The last month of the cushion

Jan 2025

12

0.9906

Discounting starts here — one month past the edge, so one month of discounting

Dec 2025

23

0.8929

Twelve months past the edge — a full year of discounting

Jan 2026

24

0.8845

The project's first savings month. $1.00 saved here counts as $0.88

Dec 2028

59

0.6355

The last savings month. $1.00 saved here counts as $0.64

6. Where every input comes from

No figure on the page is assumed or invented. Each one is either typed in by a user, read from company settings, or measured from recorded data.

Input

Source

Notes

Start date

Typed on the initiative

Month 1 of all calculations

Completion date

Typed on the initiative

Ends the build period

Useful life (years)

Typed on the initiative

Must be at least 1 year

Planned capital cost

Typed on the initiative

Must be above zero or no financial figure can be produced

Actual capital cost

Typed on the initiative

Updated as invoices arrive

Planned annual savings

Typed on the initiative

A yearly rate, not a total

Expected reduction %

Typed on the initiative

Applied to the baseline

Discount rate

Initiative → company → 12%

See section 5

Baseline emissions

Measured from linked sources

Used exactly as measured — see the warning below

Baseline costs

Measured from linked sources

Same treatment as baseline emissions

Actual emissions

Measured from linked sources

Within the measurement window only

Actual costs

Measured from linked sources

Within the measurement window only

Financial year start month

Company settings

Decides which 12 months form the baseline year

A partial baseline is used exactly as recorded. If only 6 of the 12 baseline months have data, we use that 6-month total as recorded. We do not scale it up to estimate a full year.

Why: scaling up would be inventing emissions that were never measured. Using the data as recorded means a thin baseline understates savings rather than overstating them — the safer direction to be wrong in.

What this means for you: when the baseline year is incomplete, a note appears beneath the table saying so, and the savings figures should be read as a floor — at least this much, possibly more.

7. The seven lifetime figures

These are the seven tiles in the Expected Total Project Impact card. All seven use planned inputs and cover the whole project life.

CO2e savings

How much pollution will this project avoid in total?

CO2e Savings  =  Baseline Annual Emissions  ×  Expected Reduction Percent  ×  Useful Life YearsWorked:  52,046 tCO2e/yr  ×  50%  ×  3 years  =  78,068 tCO2e

Why it is that way: the reduction percentage is applied to what the site actually emitted, then held constant for every year of the useful life. We assume the equipment performs the same each year, because we have no basis for assuming it degrades at any particular rate.

Jargon — tCO2e: tonnes of carbon dioxide equivalent. Different greenhouse gases warm the planet by different amounts, so they are all converted into the equivalent amount of carbon dioxide to give one comparable number.

Cost savings

How much money will this project save in total?

Cost Savings  =  Planned Annual Savings  ×  Useful Life YearsWorked:  $550,000/yr  ×  3 years  =  $1,650,000

Why it is that way: this is a simple total, with no discounting applied. It answers "how many dollars in total", not "what is that worth today". The discounted version of the same question is NPV, below.

Capex

What will it cost to build?

Capex  =  the planned capital cost, exactly as entered

Why it is that way: no calculation is applied. It is shown alongside the savings so the size of the investment is visible next to the size of the return.

NPV

After accounting for the fact that future money is worth less than money today, is this project ahead or behind?

Jargon — NPV (net present value): take every dollar the project spends and every dollar it saves, adjust each one for when it happens, and add them all up. A positive NPV means the project creates value. A negative NPV means it destroys value, at the discount rate being used.

For every month from the project start to the end of the useful life:    Month Amount     =  Monthly Savings  −  Money Spent That Month    Adjusted Amount  =  Month Amount  ×  that month's own Adjustment Factor
                        (a DIFFERENT number for every month — each month sits a
                         different distance from the anchor; section 5 gives the
                         formula that produces it)NPV  =  the sum of every Adjusted Amountwhere   Monthly Savings  =  Planned Annual Savings ÷ 12,  counted only during the benefit period
        Money Spent      =  the entire capital cost, in month 1 only

Every month gets a different factor — here is why. The Adjustment Factor is the share of a dollar we count for money arriving in a particular month. A factor of 1.0000 means we count the whole dollar. A factor of 0.8845 means we count 88.45 cents of it. January 2026 is 24 months after January 2024; December 2028 is 59 months after it. The further away, the longer that money has been out of reach, so the smaller its factor. There is no single factor for the project — there are 60, one per month.

Worked — every distinct step, with the middle months summarised:

Month

Months after the anchor

Amount that month

Adjustment factor

Counted as

Jan 2024 — money spent

0

−$1,000,000

1.0000

−$1,000,000

Feb 2024 – Dec 2025

1 – 23

$0

—

$0

Jan 2026 — first saving

24

$45,833.33

0.8845

$40,538

Jan 2027

36

$45,833.33

0.7897

$36,195

Jan 2028

48

$45,833.33

0.7051

$32,317

Dec 2028 — last saving

59

$45,833.33

0.6355

$29,128

All 36 saving months added together, each at its own factor

+$1,243,014

The money spent in January 2024

−$1,000,000

NPV

+$243,010

Only six rows are shown above. The full calculation has 36 saving months, each with its own factor sliding gradually from 0.8845 down to 0.6355. The four shown are simply the first, the last, and two anniversaries in between, so you can see the direction of travel.

A useful sense-check: the 36 saving months are worth $1,650,000 in plain dollars ($45,833.33 × 36). After adjustment they count as $1,243,014. The difference of $406,986 is what the 12% discount rate costs this project over its life. That is also why NPV ($243,010) is so much smaller than the plain Cost savings tile ($1.65M) minus the capex ($1M), which would suggest $650,000. Both are correct; they answer different questions.

Why the money spent is not adjusted: it leaves the bank in January 2024, which is the anchor month itself — zero months away. It is already in January-2024 dollars, so its factor is 1.0000 and the full $1,000,000 is counted.

Why it is positive here: over the full three years the discounted savings come to slightly more than the million spent. This is the answer to "is it worth doing".

IRR

What interest rate is this project effectively paying us?

Jargon — IRR (internal rate of return): the single interest rate at which this project would exactly break even. If the IRR is higher than your cost of borrowing, the project is worth doing. It lets you compare a building retrofit against, for example, a bond or a different project, on one common measure.

IRR  =  the Discount Rate at which  NPV  =  exactly zeroFound by trying rates between −99.99% and 1,000,000% and narrowing in
until the answer settles. There is only ever one such rate.

How to read it: 22.5% against a 12% discount rate means the project returns roughly double the hurdle it must clear. That is the same conclusion the positive NPV gives, expressed as a rate rather than an amount.

Why we search rather than solve: there is no direct formula for IRR with monthly cash flows. Searching is the standard method and is what spreadsheet software does internally.

When IRR cannot be produced: sometimes no rate makes NPV zero. There are two opposite reasons, and the page shows a different thing for each.

  • The project is profitable at every possible rate. Shown as >100%, meaning the return beats any hurdle you could set.

  • The project loses money at every possible rate. Shown as a dash. There is no rate of return to report.

Simple payback

How long until we get our money back?

Start a running total at zero.
Add each month's amount in turn, from the project's FIRST month.
Stop at the first month where the running total reaches zero or above.Simple Payback  =  the NUMBER OF MONTHS counted  ÷  12No reduction is applied. Every dollar counts as a whole dollar.
Worked:
Capital to recover              $1,000,000
Monthly savings                 $550,000 ÷ 12  =  $45,833.33
Savings months needed           $1,000,000 ÷ $45,833.33  =  21.8  →  22 months
Build period before savings     24 months
────────────────────────────
Total elapsed                   24 + 22  =  46 months  =  3 years 10 months

Why counting starts at the project start, not at first savings: the money leaves the bank in January 2024. The two years spent building are two years of waiting for it back. Measuring from first savings would make a two-year build appear to cost nothing in time, and would give 1 year 10 months instead of 3 years 10 months — a difference of two full years on the same project.

Why whole months: we do not estimate a part-month. The 22nd savings month is the month in which the total crosses zero, and it is counted in full (rule 3, section 4).

Discounted payback

How long until we get our money back, once we account for future money being worth less?

Exactly the same running total as Simple Payback, with one change:
before adding a month's amount, multiply it by that month's own
Adjustment Factor — the same per-month number used for NPV (section 5).Discounted Payback  =  the NUMBER OF MONTHS counted  ÷  12

Each month's $45,833.33 savings is reduced by that month's own Adjustment Factor before being added, so the running total climbs more slowly than it does for simple payback:

Month

Saved

Factor

Counted as

Running total

Month 51

Mar 2028

$45,833.33

0.6919

$31,712

−$29,310

Month 52

Apr 2028

$45,833.33

0.6854

$31,414

+$2,104

Discounted payback is 52 months, or 4 years 4 months.

Simple payback

46 months

3y 10m

Discounted payback

52 months

4y 4m

Difference

6 months

This gap is what the 12% discount rate costs the project

Why it is always longer than simple payback: each future dollar counts for less, so it takes more of them to reach the same total. Discounted payback can never be shorter.

Why show both: the gap between the two is the clearest single measure of what the discount rate is costing the project. Six months, in this example.

8. The seven to-date figures

These are the seven rows in the Project Performance to Date card. They compare what the plan said should have happened by now against what actually happened.

The rows do not all cover the same period. This table states exactly which period each row uses, and it is the single most important thing to understand about this card.

Row

Period covered

Why

CO2e reduction

Jan 2026 – Jul 2026 (7 months)

Both sides measured over the same finished months

Cost savings

Jan 2026 – Jul 2026 (7 months)

Same

Capex spend

The whole project

Capital is a one-off outlay, not a monthly rate

NPV

Jan 2026 – Jul 2026 (7 months)

Only value actually created so far

IRR

Jan 2026 – Jul 2026 (7 months)

Same

Simple payback

The whole project life

See the explanation below

Discounted payback

The whole project life

See the explanation below

Expected side, measured side

For the four windowed rows, the two columns are built differently but describe the same seven months.

Expected To Date  =  Planned Annual Amount  ×  ( Complete Months ÷ 12 )Worked:   $550,000/yr  ×  ( 7 ÷ 12 )  =  $320,833
Actual To Date  =  ( Baseline Annual Amount ÷ 12  ×  Complete Months )  −  Measured Amount In Window                    ↑ what we WOULD have spent            ↑ what we DID spend
                      over these same 7 months              over these 7 monthsWorked:   ($641,667)  −  ($450,000)  =  $191,667 saved

A common misunderstanding worth stating plainly: the Actual figure of $191,667 is already a seven-month figure. It is the difference between two seven-month amounts. It is not a yearly rate, and it must never be multiplied by 7÷12 a second time. The Expected figure is different in kind: it starts life as a yearly rate ($550,000/yr) and does need converting once. That asymmetry is correct, and it is the reason the two columns are calculated by different formulas.

Why the two payback rows cover the whole life

Payback asks one question: when do we get our money back? That is a question about the whole investment, not about the months that happen to have passed.

If we truncated both sides at today, both would read "not yet", because at seven months the plan itself has only banked $320,833 against $1,000,000 spent. The row would compare nothing against nothing, and the benchmark would disappear.

So both sides run the full project life. What differs is only the inputs:

Period

Capital cost used

Savings rate used

Expected

Full life (5 years)

Planned — $1,000,000

Planned — $550,000/yr

Actual

Full life (5 years)

Actually spent — $800,000

Measured — $328,571/yr

This gives the comparison that is actually useful: you planned to pay back in 3 years 10 months; at the rate this is genuinely saving, it will take 4 years 6 months.

Where the measured savings rate comes from:
Measured over 7 months       $191,667
Converted to a yearly rate   $191,667  ÷  7  ×  12  =  $328,571/yr

All four payback figures are measured from the same starting point — month 1, when the money was spent. In this example, the actual discounted payback would arrive after the equipment's useful life ends, so we report that it does not pay back rather than projecting beyond that limit.

The full table, explained line by line

Row

Expected

Actual

Difference

What it tells you

CO2e reduction

15,180 t

19,951 t

+31.4%

Cutting emissions faster than planned

Cost savings

$320.83K

$191.67K

−40.3%

Saving less money than planned, despite the emissions result

Capex spend

$1M

$800K

−20.0%

Came in under the planned build cost

NPV

($724.11K)

($635.18K)

+12.3%

Both negative, as expected this early. Actual is less negative because less was spent

IRR

−57.1%

−65.4%

−8.3pp

Both negative this early. The gap reflects the lower savings rate

Simple payback

3y 10m

4y 6m

—

Will take about 8 months longer than planned

Discounted payback

4y 4m

Does not pay back

—

Once discounting is applied, it does not repay within the useful life

Reading the difference column

  • The sign is always arithmetic. A minus sign means the actual number is smaller than expected. It does not by itself mean good or bad.

  • The colour carries the judgement. Green is a good outcome, red is not. On the capex row, spending less is good, so −20.0% is green.

  • "pp" means percentage points. Used on the IRR row only. Going from −57.1% to −65.4% is a fall of 8.3 percentage points. We do not express it as a percentage of a percentage, which would be misleading.

  • The payback rows show no difference. Subtracting one duration from another suggests a precision these inputs do not support, so we leave it out rather than print a misleading number.

  • Capex shows a grey difference while the project is still building. Until the project is complete, "spent less than planned" usually just means "not all the invoices are in", so no green or red judgement is applied.

Why emissions can beat plan while cost savings miss it: these two rows measure different things and can genuinely move in opposite directions. Emissions fell more than expected, but the financial saving depends on energy prices as well as volumes. If prices fell during the period, the same avoided energy is worth less money. This is a real result, not an inconsistency.

9. Every fixed number we use

These are the only values in the system that are not taken from your data. Each one is listed with where it came from.

Fixed value

Value

What it does

Where it came from

Default discount rate

12%

Used when no rate is set on the initiative or the company

The rate used throughout the reference financial model this platform reproduces. A fallback, not a recommendation.

Cushion width

11 months

Money within this many months either side of the anchor is counted in full, with no reduction

Matches the reference model, which treats amounts inside roughly a year of the anchor as equivalent to now.

Months in a year

12

Converts yearly rates into monthly amounts

Calendar fact.

Maximum discount rate

100%

Rates at or above this are rejected and shown as a dash

Chosen because a rate of 100% or more is almost always a typing error (12 entered instead of 0.12) rather than a real cost of capital.

Minimum months for an average

2

Below this, no monthly average is calculated

One reading is not an average. Two is the minimum that can be averaged at all.

Minimum months before projecting

3

Below this, the actual payback figure is labelled as an early indication

A judgement call. Seasonal billing makes one or two months an unreliable basis for projecting several years forward. The figure is still shown, but labelled.

Sparse-data threshold

50%

Below this share of months having data, a caveat is shown

A judgement call, not a derived figure. Below half a window, a monthly average describes mostly gaps.

Full baseline year

12 months

Below this, a note appears saying the baseline is incomplete

A baseline year is twelve months by definition. Anything less makes every derived saving a floor rather than an estimate.

Rounding tolerance

0.000000001

Allows the running total to count as "reached zero" when it is within a rounding error of it

Computers cannot store amounts like $45,833.33 exactly. Without this tolerance, a project whose figures divide evenly would be reported as paying back a month later than it does. The value is far smaller than a cent, so it can never accept a month that is genuinely short.

Maximum useful life

1,000 years

An upper limit on what can be modelled

A safety limit only, to stop a mistyped value from breaking the page. No real project approaches it.

Currency

Organisation setting

All money is displayed in your organisation's chosen reporting currency

Set in your company settings.

10. Known limits.

An incomplete baseline understates savings. If the baseline year is missing months, the comparison uses less data than a full year and every saving figure comes out lower than the truth. A note appears beneath the table whenever this is the case. Read those figures as a minimum.

Very early figures rest on very little. The actual payback figures project a measured savings rate across several years. Early in a project that rate is based on only a few months of bills. Below three complete months the figure is labelled to say so, but the underlying caution applies for longer than that.

Two payback rows sit in a table headed "to date". As explained in section 8, this is deliberate and the alternative is worse. It is nonetheless the one place where the card's heading is not literally true of every row, and it is worth pointing out when sharing a screenshot of the table.

The same initiative may show different values on different pages. The initiative detail page values money in the project's own start month; the Scenario Planner values it in today's money. Both are correct for their purpose, and both state their basis on screen. When quoting a figure, quote the page it came from.

Did this answer your question?